Solar power and clean water for the campus

A solar power plant, borehole and reticulation that supply the whole campus with affordable energy and clean water, and teach renewable energy skills.

Category
Campus infrastructure
Where
Binga campus
Planned dates
3 Jan 2027 to 3 Jan 2028
People who benefit
400
Funding sought
USD 123,000
Raised so far
USD 0 (0%)
Project owner
Takura Trust

Overview

A solar power plant, borehole and reticulation that supply the whole campus with affordable energy and clean water, and teach renewable energy skills.

Every BICA service needs power and water. This project installs a solar plant with batteries, a borehole and water reticulation, and trains learners in renewable-energy trades on the real system.

USD 0 of USD 123,000 sought

Proposal

1. Executive summary

The project installs a 60 kW solar plant with battery storage, a solar-powered borehole and a campus water network, with a metering and monitoring system. It supplies Haven, Anchor, Golden Years, Nest, New Dawn, the Academy and the farm with reliable, low-cost power and clean water, and becomes a training ground for solar and plumbing learners.

2. Background and need

Power cuts and unreliable water disrupt clinics, kitchens, cold rooms and classes across Zimbabwe. Diesel generators are costly and pollute. Binga receives some of the highest sunshine in the country.

3. Problem statement

Without reliable power and water, BICA cannot run its cold rooms, clinic, computer lab and workshops, or care for people safely. Each outage costs money and puts people at risk.

4. Goal and objectives

Goal: all BICA services run on reliable, clean and affordable energy and water.

Objectives: (1) a 60 kW solar plant and batteries; (2) a borehole and water network serving the campus; (3) cut fuel costs by 80 per cent; (4) train 40 learners a year in solar and water trades.

5. Who will benefit

Everyone who lives, learns or works on campus, about 400 people, and 40 Academy learners a year in renewable-energy and plumbing trades.

6. Approach and activities

A qualified installer designs and installs the plant, borehole and network under supervision, with Academy learners working as assistants. The system is metered by building, and monthly readings are published. A maintenance contract covers the first two years while BICA technicians are trained to take over.

7. Monitoring, evaluation and learning

Progress is measured against the indicators in the results framework. The project manager keeps a monthly record of activities, spending and results, and reviews it with the Director. Baseline figures are taken in the first month, and the same measures are repeated at the mid-point and at completion. Beneficiaries are asked for their views at least twice a year, and what they say changes the plan.

A short evaluation by someone independent of BICA is carried out at the end, and its findings, including what did not work, are shared with the funder and published on this website.

8. Sustainability and exit

Savings on fuel and grid power repay the investment within a few years, and a maintenance fund is set aside from the savings. The plant is insured, and trained technicians keep it running.

9. BICA capacity and governance

BICA, the Binga Institute of Conservation Agriculture, is an institution of Takura Trust, which owns the project and holds it to account. The Trust's board provides oversight, approves budgets and receives quarterly progress and financial reports. On site, the Director leads heads of care, agriculture, the Academy, enterprise, finance and partnerships, with a safeguarding and monitoring officer. A Clinical and Recovery Advisory Panel reviews care protocols and outcomes.

Funds given for this project are restricted: they are recorded in a separate project ledger, spent only against the approved budget, supported by quotations and receipts, and open to independent audit. Funders receive a narrative and financial report each quarter and a final report at completion.

10. Safeguarding and risk management

Everyone who works or volunteers on this project is vetted and signs the BICA safeguarding policy before starting. There is a named safeguarding officer, a confidential way to raise concerns, and a duty to report to the police and the Department of Social Development where required. Children, young mothers and elders are never left alone with an unvetted adult.

The main project risks are listed in the risk register with the action we will take and the person responsible. Risks are reviewed monthly by the project manager and quarterly by the Trust board.

Work plan

Phases

PhaseFromTo
Design and procurement3 Jan 20272 Mar 2027
Installation3 Apr 20272 Sep 2027
Commissioning and training3 Sep 20272 Jan 2028

Tasks

TaskFromTo
Energy and water survey; design3 Jan 20272 Mar 2027
Borehole drilled and tested3 Mar 20272 May 2027
Solar plant and batteries installed3 May 20272 Sep 2027
Water network completed3 Jun 20272 Sep 2027
Technicians and learners trained3 Oct 20272 Jan 2028

Milestones

MilestoneDueEvidence
Borehole commissioned3 May 2027Signed report with photographs
Solar plant switched on3 Sep 2027Signed report with photographs
Final report and review3 Jan 2028Signed report with photographs

Budget

ItemUnitQtyUnit costTotalRequested
Management6,000.00
Project coordination and reportingmonth12500.006,000.003,000.00
Monitoring3,000.00
Monitoring, evaluation and auditlot13,000.003,000.003,000.00
Solar plant86,300.00
Solar panels, inverters and mounting (60 kW)kW60620.0037,200.0037,200.00
Battery storage (120 kWh)kWh120330.0039,600.0039,600.00
Wiring, protection and meteringlot19,500.009,500.009,500.00
Training5,200.00
Training for 40 learners and 6 technicianslot15,200.005,200.005,200.00
Water25,500.00
Borehole drilling, casing and test pumpingm10070.007,000.007,000.00
Solar pump, tank and reticulationlot118,500.0018,500.0018,500.00
Total budget (USD)126,000.00123,000.00

Requested from the funder: USD 123,000 (98%). BICA and partners contribute USD 3,000.

When the funds are needed

Quarter of the projectRequested (USD)
Quarter 110,000.00
Quarter 2104,800.00
Quarter 35,200.00
Quarter 43,000.00

Results and risks

Results framework

LevelResultIndicatorNowTargetHow we check
GoalServices run on reliable clean power and waterHours of outage per monthNot measuredUnder 4Meter logs
OutcomeFuel and grid costs fallReduction in energy cost0%80%Accounts
OutputSolar plant, borehole and network workingCommissionedNoYesCommissioning certificate
OutputLearners trainedLearners certified040Certificates

Risks and what we will do

RiskScoreWhat we will do
Borehole yield is lower than expected12Siting survey, test pumping and a second site as a backup.
Equipment price rises9Fix prices early and hold a contingency.
Theft of panels or batteries8Fencing, lighting, guard, insurance and tracking.

Funding and owner

Project owner

Owner
Takura Trust
Implemented by
Binga Institute of Conservation Agriculture (BICA)
Telephone
+263774114107
Address
Binga District, Matabeleland North, Zimbabwe

Every funder receives a progress and financial report each quarter. Funds are restricted to this project and tracked in a separate ledger.